Townline Road construction beginning July 7

By WEEK Producer

Townline Road construction beginning July 7

June 27, 2014 Updated Jun 27, 2014 at 5:11 PM CDT

PEORIA, Ill. – Construction on Townline Road is set to kick off July 7.

Townline Road, from 340 feet of Industrial Road to University Street will be reconstructed.

Entrance walkways, driveway approaches and retaining walls are set to be removed and replaced by the city.

During the first stage of construction, the eastbound lane will be closed. In the second stage, the westbound lane will be closed.

The stages are estimated to take about a month each.

Property owners affected by the project are invited to attend a public forum on Wednesday, July 2 at 2 p.m. at Peoria Production Shop, 2029 W. Townline Road.